This is the Bowie city manager's report for Feb. 25.

The week of March 13 will be a busy week. We have two bid openings for March 13.

The first one is for phase two of the sewer line project. This will cover new sewer lines for the following streets: Coffield, Strong, Roach, Hudspeth and the alley behind Hulme. We still have not gotten an easement for the Glen Hills lift station from the property owners, but the city attorney is working with the owners to finally get that.

The second bid opening is for the Downtown Revitalization project for a section of Smythe Street. The plans were finally approved and it was put out for bid.

Work at the substation transformer project has come to a halt. We kept having the same problems of getting the necessary components, so Electric Department Head Jay Evans sent the contractor home until all the necessary equipment was in place, and then it would be completed, which would take about a month or two, depending on when the contractor and transformer crew could come back.

Luckily, we have had very few problems with the extremely cold weather. Most of the crews are staying in and cleaning up their respective shops. The guys are looking forward to spring.